The timeline below will be updated throughout the project with newer items added to the top of the page. You can click a photo to view a larger image of it. I have not taken the time to caption each of these images but if you have a question please do not hesitate to write.
- Mar. 2018Landscaping installation, House 3 – closed in windows, complete electrical, pressure test and green board (drywall) going up.
- Feb. 2018Final irrigation system details, landscaping preparation, seawall completion & House 3 windows.
- Jan. 2018Surgery, Electrical to Meters, Nightstands done, Irrigation System going in, Permanent Electrical to Manager’s Unit.
- Dec. 2017Final Floor Pours, Trenching for Electric & Water, Irrigation Well, Adding Palmetto, Tile Work, Electric Cables & Water pipes in.
- Nov. 2017Tile, Always sand, Manager’s Kitchen / Closets / Furniture Example (bed), Floor pours, White Concrete, Creating Fill, Buffing Floors, Framing Ceilings and Plastering.
- Oct. 2017Manager’s Unit finishing up, Sand & more sand, Tile & Plaster work.
- 10/3/2017Doors Installed – Manager’s Unit, Garage Doors, Exterior Tile Grouted, Baseboards, Gate Painted, House 3 plastering.
- 09/30/2017Kitchen Counters & Exterior Tile.
- 09/28/2017House 4 Plastered, Framing House 3, Electrical & Tile.
- 09/22/2017Vanity, Kitchen Counters & Gate.
- 09/14/2017A few finish details, vanity, counters & patio.
- 09/12/2017AC Units & Outdoor Shower.
- 09/08/2017Vanities & Floor Pour.
- 09/06/2017Patios, Septic(s) and House 4 Plastering.
- 09/04/2017Patios, Test Patio Finish and Manager’s Unit Stairs.
- 09/01/2017House 2 Prime & Patio Foundations.
- 08/31/2017Manager’s Unit Coming Together, Patios on Houses going in.
- 08/25/17House 2 plastering done & Birth of a septic tank.
- 08/17/2017Landscape Design Plan.
- 08/15/2017Windows MU, Septics.
- 08/09/2017Manager’s Unit Septic & Electrical.
- 08/07/2017Manager’s Unit 1st Floor & First Septic Base.
- 08/06/2017Manager’s Unit Kitchen, Septic, Priming, etc.
- 08/03/2017Framing, Septic Mold & Kitchen 2.
- 08/02/2017House 2 Kitchen Pour (not end-product), Manager’s Unit Floor Prep & Concrete work.
- External Concrete Work
- Manager’s Unit Floor Prep
- House 2 Kitchen Pour
- House 2 Kitchen Pour
- House 2 Kitchen Pour
- House 2 Downstairs Bath Vanity Pour
- 08/01/2017More Kitchen Forms & Test Floor Patch.
- Kitchen Forms – Stage 3
- Concrete Floor – Test Patch – Rough
- Kitchen Form – Manager’s Unit
- 07/31/2017Concrete, Kitchen Forms & Plumbing.
- Concrete Work
- Automation? Not in Belize.
- Kitchen Forms – Stage 2
- Plumbing – Managers – Garage
- 07/29/2017Kitchen Forms & Framing.
- Kitchen Forms – Stage 1
- Second Floor Framing – House 2
- Stairwell from top
- 07/26/2017Framing, Kitchen Layout & Floor Aggregate.
- Aggregate for Floors
- Kitchen Layout
- Kitchen Layout
- Framing
- Framing
- Framing
- Framing
- Framing
- 07/21/2017Landscape Design Planning Weekend.
- Landscape Design Weekend
- 07/18/2017Third Floor Managers Unit & Misc.
- Framing in the ceiling
- Plaster work
- Roof
- Plaster work
- Plaster work
- Overall View
- Plumbing – House 2 – Upstairs Bath
- Electrical Fill In
- 07/15/2017Endless Concrete & Manager’s Unit Roof.
- 07/12/2017Concrete & Covintec.
- 07/03/2017Starting Roof Deck Walls – House 1.
- 06/30/2017Pouring Roof on House 1.
- 06/26/2017Second Floor Pics.
- 06/23/2017Openings will be railings.
- 06/17/2017Still Going Up.
- 06/14/2017Rebar & Plastering.
- 06/02/2017Preparing roofs for slab.
- 05/25/2017Pouring Roofs.
- 05/24/2017Conduit/Wiring & Misc.
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- 05/23/2017Pouring Garage Roof.
- 05/19/2017Reaching for the roofs.
- 05/12/2017Second floor underway on 4 out of 5 structures.
- 05/08/2017Preparing House 3 for Slab Pour & 2nd Floor Walls on House 1 & 2.
- 05/02/2017Materials & Walls going up.
- 04/26/2017House 1 – Second Floor Slab Pour & Apt.
- 04/22/2017House 2 – Second Floor Slab Pour.
- 04/21/2017Slab & Stair Pour – Utility Garage & Apt.
- 04/19/2017Slab & Stair Pour – Utility Garage & Apt.
- 04/05/2017Beams & Insulation going in for 1st floor slab.
- 04/01/2017Coming along.
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- OLYMPUS DIGITAL CAMERA
- 03/28/20171st floor beams & styrofoam insulation arrive.
- 03/24/2017Still at it.
- 03/17/2017Nearly ready for 1st floor ceiling beams.
- 03/14/2017First floor walls getting close to completion.
- 03/10/2017Framing to pour columns.
- 03/08/2017Continuing upward – 1st floor walls.
- 03/04/2017First floor walls continue upward.
- 03/02/2017First floor walls going up.
- 02/28/2017Final slab work & start of walls.
- 02/27/2017Paperwork filed with Lands Department, Belmopan.
- 02/23/2017Central Bank approval received for purchase from foreign entity (Chianti, Ltd.).
- 02/22/2017Utility garage footers & slab work.
- 02/21/2017Continued plumbing, electrical and slab prep.
- 02/18/2017Continued plumbing, electrical and slab prep.
- 02/17/2017Plumbing, electrical & slab pours.
- 02/16/2017Plumbing, electrical & preparing for slab pours.
- 02/06/2017Backfill & foundation work.
- 02/04/2017Continued foundation work.
- 02/01/2017Block to ground floor slab.
- 02/01/2017Plans finalized by architect.
- 1/24-25/2017Foundation work.
- 01/19/2017Laying out forms for foundations.
- 01/08/2017+Material acquisition & rain.
- 01/07/2017Broke ground.
- 12/29/2016Sited houses on property.
- 12/20/2016Lagoon’s Edge, Ltd. incorporated.
- 12/15/2016+Iterative process on house plans.
- 12/15/2016Keila Martinez, Architect hired.
- 12/13/2016Signed construction contracts with MSG Construction.
- 12/12/2016Cut road into property.
- Cutting in the Road
- Utility Garage
- 12/11/2016Draft contract from Martin Galvez received.
- 12/09/2016Closed on property.
- 12/07/2016House plans updated to include 3rd bedroom.
- 12/05/2016Final quote on houses received from Martin Galvez.
- 11/28/2016+Title verification & legal work.
- 11/26/2016Offer accepted.
- 11/25/2016Second offer on property made.
- 11/20/2016+Alternatve properties investigated.
- 11/20/2016Preliminary house plan identified.
- 11/19/2016Initial offer made on property. Offer rejected.
- 11/15/2016Martin Galvez informed David Santilli of property for sale..